WAPDA completes Golen Gol-Timergara transmission line
Pakistan Water and Power Development Authority (WAPDA) has succeeded in completing the most difficult transmission line from Golen Gol, Chitral to Timergara for evacuation of power generated by Golen Gol Hydropower Project to the national grid.
Talking to media, WAPDA spokesman said the 180-kilometer long Golen Gol-Timergara transmission line crosses through the most difficult mountainous terrain having extreme weather conditions.
The transmission towers in Pakistan have never been erected earlier at this altitude.
He said Golen Gol Hydropower Project will provide 436 million units of electricity to the National Grid every year.
Benefits of the project have been estimated at 3.7 billion rupees per annum.
Related News
Equipping youth with digital skills top priority
ISLAMABAD, 15 JULY (DNA) — Federal Minister for Information Technology and Telecommunication Shaza Fatima KhawajaRead More
No entry to Pakistan on expired Nicop under new travel rules
LONDON: Pakistan has clarified that overseas Pakistanis travelling on foreign passports will continue to beRead More


Comments are Closed