Pakistan Water and Power Development Authority (WAPDA) has succeeded in completing the most difficult transmission line from Golen Gol, Chitral to Timergara for evacuation of power generated by Golen Gol Hydropower Project to the national grid.
Talking to media, WAPDA spokesman said the 180-kilometer long Golen Gol-Timergara transmission line crosses through the most difficult mountainous terrain having extreme weather conditions.
The transmission towers in Pakistan have never been erected earlier at this altitude.
He said Golen Gol Hydropower Project will provide 436 million units of electricity to the National Grid every year.
Benefits of the project have been estimated at 3.7 billion rupees per annum.
Related News
PM Shehbaz clinches landmark Saudi agri-export agreement
ISLAMABAD, AUG 30 /DNA/ – In a major diplomatic and economic breakthrough, Prime Minister MuhammadRead More
PM, Nawaz hold second meeting
DNA Lahore: Former Prime Minister Nawaz Sharif and incumbent Prime Minister Shehbaz Sharif convened theirRead More


Comments are Closed